SHIP SHAPE: { Resources | Payroll Services | CSCS | Construction | Investments }

Building Terms

Building term definitions, organised by category:


Building Terms: Surveying / Professional

Bills of quantities
A set of description of the materials and labour needed for construction work. Bills of quantities are prepared by a quantity surveyor for tendering purposes. They provide a common basis for contractors when estimating prices, as well as in the settlement of the final account.
Top
Conditions of contract
A contract document which describes contract matters in detail. It can have many clauses, covering rights and obligations of interested parties, usually taken from a standard form of contract.
Top
Contingency sum
A provisional amount in bills of quantities for unforeseeable work.
Top
Direct labour
Tradesmen and labourers employed immediately by the client or his agent, without the involvement of a contractor.
Top
Domestic sub-contractor
A sub-contractor selected by the contractor
Top
Estimate
The probable cost of project, usually arrived at using bills of quantities and applying a margin.
Top
Fix only
To install objects supplied and delivered to site by the client.
Top
Main contractor.
The contractor who has the main contract with the client and is thus responsible for all work on site, including that of sub-contractors. This is typically facilitated through a site foreman.
Top
Nominated sub-contractor
A company nominated by the client, not the main contractor. They are directly responsible to the client, not to the main contractor.
Top
Nominated supplier
A supplier selected by the client.
Top
Overheads
The costs of utilities, accounting, director's fees, etc., which cannot fairly be charged to one job and must therefore be distributed as a percentage over the flat cost of all items in a contract.
Top
Practical completion
The stage at which a project is ready for handover. It must be reasonably fit for occupation, and minor defects may still be put right provided they cause no inconvenience to the owner. The issue of the certificate of practical completion starts the defects liability period, although it is not uncommon for the commissioning of services to continue for some time afterwards.
Top
Pre-contract stage
The time before work begins on site. Tendering, sub-contracting, pre-ordering etc.
Top
Preliminaries
The project administration and site equipment required for work to go ahead or to be properly completed, but not part of the work. The cost of preliminaries is often partly reimbursed by an advance. This typically includes office overheads, giving notices, paying fees, taking out insurance, removing rubbish etc.
Top
Provisional sum
An amount of money in bills of quantities to provide for items or work for which an exact price cannot be obtained or which will be subject to re-appraisal.
Top
Special attendance
Use of the main contractor's plant or equipment by a sub-contractor normally charged per hour.
Top
Sub-contractor
A company or an individual employed by the main contractor to perform a sub-contract. The client can also select nominated sub-contractors
Top
Supply and fix
A process whereby the same firm supplies and installs materials.
Top
Variation
A change in the quantity or quality of, or time allowed for, the work agreed to in a contract.
Top

This information is provided for your general interest only. Ship Shape Construction disclaims all responsibility and liability (including for negligence) in relation to use of the information on this site.